Additions and Renovations

Conversion of King High School to King Middle School

Once the new high school is completed, the current King High School campus will be converted to the new King Middle School.

 
Conversion of KMS to Educational Support Building

C.E. King Middle School will be repurposed for alternate district use(s). As the renovation of the existing C.E. King High School project develops, the district will continue to assess their district-wide facility needs.  More information will follow as the planning continues to progress. 
 

Extended Parent Pickup Lanes

Site renovations at Early Childhood Academies to allow additional on-site queuing for parent pickup.

Schools Included:

Stephanie Craven Early Childhood Academy
Sheldon Early Childhood Academy


Extended Student Loading/Unloading Canopies at Early Childhood Academies

Extend canopies over existing walkways for student drop-off and pickup.

Schools Included:

Stephanie Craven Early Childhood Academy
Cravens ECA Canopy Extension
 
Sheldon Early Childhood Academy 
Sheldon ECA Canopy Extension

Buses/Student Mobility 

Within the next five years, Sheldon ISD anticipates purchasing at minimum fifteen new school buses.

Timeline

Projects 2016 2017 2018 2019 2020
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Additions and Renovations
Conversion of King H.S. to King M.S.
Conversion of KMS to Educational Support Building    
Extended Parent Pickup Lanes at ECAs
Extended Student Loading/Unloading
Buses/Student Mobility

Legend: Planning Design Construction Completion